A 1952 town hall, rebuilt in eight and a half months

Llinars del Vallès rebuilt its 1952 town hall in 8.5 months, co-funded by NextGenerationEU. Catalonia’s first EnerPHit certified office building.

A 1952 town hall, rebuilt in eight and a half months

In January 2024, Llinars del Vallès started work on its town hall with a deadline it could not move. The building on the Plaça de la Vila dated from 1952, around 955 m² over three floors, and it had the problems you would expect: solid walls with no insulation, original windows, and four separate citizen service desks spread through a plan that had grown by accretion. By 16 September the works had to be finished, or the European funding paying for three quarters of them would be lost.

It got finished. The building is now the first administrative building in Catalonia certified to the Passivhaus EnerPHit standard, in the Plus class.

Side by side comparison of the town hall facade before and after the retrofit
The same elevation before and after: bare masonry and original windows, then an insulated envelope.

A fixed budget and a fixed date

The works cost 804,650 € including VAT, about 842 € per square metre. Of that, 601,750 € came from the Recovery, Transformation and Resilience Plan, funded by the European Union through NextGenerationEU, and 202,900 € from the council’s own budget. The grant set both the ceiling and the calendar: four months to produce the design, eight and a half to build.

That matters more than it sounds. A deep energy retrofit is usually sold as something slow and disruptive. This one was programmed like any other municipal contract, in a building that stayed in use.

Wrapping a building that was never designed to be wrapped

The façades were insulated from the outside with Ytong Multipor mineral insulation board — 120 mm on the main brick elevations, 80 to 100 mm where the geometry was tighter — taking the walls from bare masonry to between 0.24 and 0.41 W/(m²K). The flat roofs received 80 mm of XPS over 40 mm already there; the pitched roofs 100 mm, giving 0.26 to 0.28 W/(m²K). A liquid applied membrane was taken around the whole envelope behind the insulation to form a continuous airtight layer.

Close up of mineral insulation board being fixed over a liquid applied membrane at the foot of a wall
Mineral insulation board going on over the continuous airtight membrane at the base of the wall.

Insulating from the outside rather than the inside was the decision that made the rest possible. It keeps the existing masonry inside the warm envelope, where its weight steadies the internal temperature through a Vallès summer. It leaves the junctions accessible, so they can be resolved rather than worked around. And it costs the council nothing in floor area, which in a building where four service desks were being consolidated into one mattered as much as the energy.

Every window was replaced with triple glazed, low-e, argon filled Smartwin timber-aluminium units made by Ventanas Gardea, installed at 1.27 W/(m²K) including frames and fixing. The insulation was returned into the reveals, so the frames sit within the insulation line rather than at the edge of it.

Diagram of the floor to wall junction showing continuous insulation and the calculated thermal bridge value
The slab-to-wall junction, with the insulation line carried through. Linear thermal bridge coefficient 0.096 W/(m·K).

The junctions decide the result

Insulation thickness is the easy part. What determines whether a retrofit performs is what happens where elements meet, and in a 1950s building those junctions were never detailed for it.

Two-dimensional thermal bridge calculations were made to ISO 10211 for the critical details. At the slab to wall junction the linear thermal bridge coefficient came out at 0.096 W/(m·K), with a temperature factor of 0.766 against a required minimum of 0.31 for this climate. The minimum internal surface temperature in that detail is 15.3 °C when it is freezing outside, which is what keeps condensation and mould off it.

Checked rather than assumed

A certified building is not one where the design intent was good. It is one where every number was traced back to something real before it was accepted.

The energy model is rebuilt against evidence: conductivity values taken from the data sheets for the boards actually delivered to site, window performance from the installed units including frames and fixings rather than the glass alone, heat recovery from the ventilation unit’s own component certificate rather than a brochure figure, areas checked against site photographs. Where a value cannot be evidenced, it does not go into the model.

Then the two things that cannot be modelled are measured. Airtightness is tested on the finished building, not declared. Ventilation flow rates are commissioned and measured room by room, because a heat recovery unit that is 84% efficient on paper recovers nothing useful if the system is unbalanced.

That is the difference between a building that should perform and one that does.

Every gap in the building, added up

On 15 October 2024 the completed building was tested with a blower door. Air is pushed in and drawn out at a range of pressures and the leakage is measured against the internal volume, here 2,346 m³, inside an envelope of 1,428 m².

The result was n50 = 0.88 air changes per hour, measured, against a limit of 1.04 for this project. That is 2,065 m³/h of air leaking at 50 pascals.

The number that makes it real is the equivalent leakage area. Add every crack, service penetration and badly closing joint in the building together and they come to 0.0629 m²: a single square hole about 25 cm by 25 cm, in a 1,428 m² envelope that was built in 1952.

Graph of the measured air change rate against the certification limit, with the equivalent leakage area shown to scale
The measured airtightness result against the limit, and the leakage area it represents.
Mechanical ventilation unit with large insulated ducts on a flat roof during installation
The ventilation unit and its ductwork being installed on the roof.
Office workspace with timber framed triple glazed windows and desks along a wall
An office on the upper floor: daylight, triple glazing and continuous filtered air.

Air, heat and cold

Ventilation is a Zehnder Carma unit on the roof, Passivhaus certified, recovering 84% of the heat from the air it extracts. It runs continuously and filters what it brings in, which in an office with a public counter is as much about air quality as about energy.

It was commissioned in March 2025 and measured room by room: 2,351 m³/h supplied against 2,330 designed, and 2,357 m³/h extracted. Balanced to within one percent of the design, which is where heat recovery either works or does not.

Heating comes from the municipal biomass district network through wall mounted fan coils. The same fan coils provide cooling in summer from a chiller on the roof. A Loxone system monitors energy use and indoor air quality in real time.

Solar, and what it covers

There is 19.3 kWp of photovoltaic on the roof: 13.6 kWp installed as part of the works, alongside 5.7 kWp already there. Together they produce about 25,300 kWh a year against a building demand of around 36,300 kWh, roughly 70% of everything the building uses, in final energy. In the certification’s terms, the building generates 67 kWh/(m²·a) per square metre of building footprint of renewable energy against a renewable primary energy demand of 43 kWh/(m²·a), per square metre of treated floor area, which is what earns the Plus class.

Photovoltaic panels mounted on the roof of the town hall
The photovoltaic array on the roof, 19.3 kWp in total.

What the certificate says

Measured against a treated floor area of 761 m², and against the EnerPHit criteria for this climate:

Heating demand came in at 18 kWh/(m²·a) against a limit of 20. Cooling and dehumidification at 4 against 15. Excessive humidity occurs 4% of the year against a limit of 10%. Airtightness, 0.88 against 1.04.

Not one of them is a near miss, and all of them are on a building from 1952.

Graph comparing the certified heating demand, cooling demand, humidity frequency and airtightness against their limits
The certified results against the EnerPHit criteria for this climate.
The town hall seen from the public square with trees and planters in front
The building back in use on the square it has stood on since 1952.

The point

A municipality with a capped budget and a hard deadline took a post-war office building and got a certified deep retrofit out of it in eight and a half months. The people working there have stable temperatures, filtered air and daylight; the council has an asset worth more and a running cost a fraction of what it was.

There are a great many town halls like this one.

Short version

1952 town hall, around 955 m², retrofitted in eight and a half months for 804,650 € with NextGenerationEU funding. 120 mm external mineral insulation, triple glazing, n50 = 0.88, 84% heat recovery, 19.3 kWp of solar. Heating demand 18 kWh/(m²·a). Catalonia’s first EnerPHit certified administrative building, Plus class.

Praxis Resilient Buildings carried out the Passivhaus certification and the airtightness testing on this project.

Project page: Ajuntament Llinars del Vallès, Catalonia, EnerPHit Plus retrofit